DEL CITY, OK · Oklahoma County
SKYLINE MHP Water System
Current status
1 item on record is open and awaiting resolution as of July 4, 2026. None are health-based violations — open items of this kind are most often monitoring or reporting requirements, not water-safety findings. Full details are in the violation history below.
This system's next federally required Consumer Confidence Report is due July 1, 2027, under the EPA's revised reporting rule.
Data sourced from the EPA ECHO database (SDWA bulk download), last refreshed July 4, 2026. This is a record-keeping and public-information tool — it does not replace Oklahoma’s official records. Always confirm current status with Oklahoma before making decisions based on this information.
System facts
- System ID (PWSID)
- OK2005542
- System type
- Community Water System
- Population served
- 120
- Service connections
- 99
- Ownership
- privately owned
- Water source
- groundwater (wells)
Violation history
Monitoring, Regular
—BHC-GAMMA
January 1, 2025 – March 31, 2025
ResolvedMonitoring, Regular
—Methoxychlor
January 1, 2025 – March 31, 2025
ResolvedMonitoring, Regular
—Endrin
January 1, 2025 – March 31, 2025
ResolvedMonitoring, Regular
—Chlordane
January 1, 2025 – March 31, 2025
ResolvedMonitoring, Regular
—Total Polychlorinated Biphenyls (PCB)
January 1, 2025 – March 31, 2025
ResolvedMonitoring, Regular
—HEXACHLOROBENZENE
January 1, 2025 – March 31, 2025
ResolvedMonitoring, Regular
—Heptachlor epoxide
January 1, 2025 – March 31, 2025
ResolvedMonitoring, Regular
—Heptachlor
January 1, 2025 – March 31, 2025
ResolvedMonitoring, Regular
—LASSO
January 1, 2025 – March 31, 2025
ResolvedMonitoring, Regular
—Atrazine
January 1, 2025 – March 31, 2025
ResolvedMonitoring, Regular
—Hexachlorocyclopentadiene
January 1, 2025 – March 31, 2025
ResolvedMonitoring, Regular
—Simazine
January 1, 2025 – March 31, 2025
ResolvedMonitoring, Regular
—Toxaphene
January 1, 2025 – March 31, 2025
ResolvedLSL Reporting
—LEAD AND COPPER RULE REVISIONS
October 17, 2024 – July 15, 2025
ResolvedLSL Inventory
Health-basedLEAD AND COPPER RULE REVISIONS
October 17, 2024 – July 15, 2025
ResolvedMonitoring, Regular
—LASSO
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Chlordane
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—ETHYLENE DIBROMIDE
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—1,2-DIBROMO-3-CHLOROPROPANE
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Total Polychlorinated Biphenyls (PCB)
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Pentachlorophenol
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Benzo(a)pyrene
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—HEXACHLOROBENZENE
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—2,4,5-TP
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—2,4-D
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Heptachlor epoxide
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Heptachlor
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Atrazine
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Carbofuran
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Hexachlorocyclopentadiene
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Di(2-ethylhexyl) phthalate
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Simazine
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—OXAMYL
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Di(2-ethylhexyl) adipate
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Diquat
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Dalapon
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Methoxychlor
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Regular
—Endrin
October 1, 2024 – December 31, 2024
ResolvedMonitoring, Routine (RTCR)
—Revised Total Coliform Rule
August 1, 2024 – August 31, 2024
ResolvedMonitoring and Reporting (DBP)
—Chlorine
August 1, 2024 – August 31, 2024
ResolvedMonitoring, Regular
—Benzo(a)pyrene
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—HEXACHLOROBENZENE
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—LASSO
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Atrazine
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Carbofuran
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Hexachlorocyclopentadiene
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Dinoseb
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Picloram
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Di(2-ethylhexyl) phthalate
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Simazine
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—OXAMYL
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Di(2-ethylhexyl) adipate
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Glyphosate
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Endothall
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Diquat
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Dalapon
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Toxaphene
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Methoxychlor
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—BHC-GAMMA
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Regular
—Endrin
July 1, 2024 – September 30, 2024
ResolvedMonitoring and Reporting (DBP)
—Chlorine
July 1, 2024 – July 31, 2024
ResolvedMonitoring, Regular
—Total Polychlorinated Biphenyls (PCB)
July 1, 2024 – September 30, 2024
ResolvedMonitoring, Routine (RTCR)
—Revised Total Coliform Rule
July 1, 2024 – July 31, 2024
ResolvedMonitoring, Routine (RTCR)
—Revised Total Coliform Rule
June 1, 2024 – June 30, 2024
ResolvedMonitoring and Reporting (DBP)
—Chlorine
June 1, 2024 – June 30, 2024
ResolvedMonitoring and Reporting (DBP)
—Chlorine
April 1, 2024 – June 30, 2024
ResolvedMonitoring and Reporting (DBP)
—Chlorine
April 1, 2024 – June 30, 2024
ResolvedMonitoring and Reporting (DBP)
—Chlorine
January 1, 2024 – March 31, 2024
ResolvedMonitoring and Reporting (DBP)
—Chlorine
January 1, 2024 – March 31, 2024
ResolvedConsumer Confidence Report Inadequate Reporting
—Consumer Confidence Rule
October 2, 2023 – June 30, 2024
ResolvedMonitoring and Reporting (DBP)
—Chlorine
October 1, 2023 – December 31, 2023
ResolvedMonitoring, Source Water (GWR)
—E. COLI
July 13, 2023
UnaddressedMonitoring, Routine (RTCR)
—Revised Total Coliform Rule
July 1, 2023 – July 31, 2023
ResolvedMonitoring and Reporting (DBP)
—Chlorine
July 1, 2023 – September 30, 2023
ResolvedMonitoring and Reporting (DBP)
—Chlorine
July 1, 2023 – September 30, 2023
ResolvedMonitoring and Reporting (DBP)
—Chlorine
July 1, 2023 – September 30, 2023
ResolvedMonitoring and Reporting (DBP)
—Chlorine
April 1, 2023 – June 30, 2023
ResolvedMonitoring and Reporting (DBP)
—Chlorine
April 1, 2023 – June 30, 2023
ResolvedMonitoring and Reporting (DBP)
—Chlorine
April 1, 2023 – June 30, 2023
ResolvedMonitoring and Reporting (DBP)
—Chlorine
January 1, 2023 – March 31, 2023
ResolvedMonitoring and Reporting (DBP)
—Chlorine
January 1, 2023 – March 31, 2023
ResolvedMonitoring, Routine (RTCR)
—Revised Total Coliform Rule
January 1, 2023 – January 31, 2023
ResolvedConsumer Confidence Report Inadequate Reporting
—Consumer Confidence Rule
October 2, 2022 – June 30, 2024
ResolvedMonitoring and Reporting (DBP)
—Chlorine
October 1, 2022 – December 31, 2022
ResolvedMonitoring, Routine (RTCR)
—Revised Total Coliform Rule
July 1, 2021 – July 31, 2021
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2021 – June 30, 2024
ResolvedMonitoring and Reporting (DBP)
—Chlorine
July 1, 2021 – September 30, 2021
ResolvedConsumer Confidence Report Inadequate Reporting
—Consumer Confidence Rule
October 2, 2020 – June 30, 2024
ResolvedMonitoring and Reporting (DBP)
—Chlorine
October 1, 2020 – December 31, 2020
ResolvedMonitoring and Reporting (DBP)
—Chlorine
January 1, 2020 – March 31, 2020
ResolvedMonitoring, Routine (RTCR)
—Revised Total Coliform Rule
January 1, 2020 – January 31, 2020
ResolvedConsumer Confidence Report Inadequate Reporting
—Consumer Confidence Rule
December 2, 2019 – June 30, 2024
ResolvedMaximum Contaminant Level Violation, E. coli (RTCR)
Health-basedRevised Total Coliform Rule
November 1, 2016 – November 30, 2016
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2016 – June 30, 2017
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
November 1, 2015 – November 30, 2015
ResolvedMonitoring and Reporting (DBP)
—Chlorine
October 1, 2015 – December 31, 2015
ArchivedMonitoring, Source Water (GWR)
—E. COLI
September 18, 2015 – April 16, 2018
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
August 1, 2015 – August 31, 2015
ResolvedMonitoring, Source Water (GWR)
—E. COLI
July 24, 2015 – April 16, 2018
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2015 – June 30, 2017
ResolvedMonitoring and Reporting (DBP)
—Chlorine
July 1, 2015 – September 30, 2015
ArchivedMonitoring, Repeat Major (TCR)
—Coliform (TCR)
July 1, 2015 – July 31, 2015
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
November 1, 2014 – November 30, 2014
ResolvedMonitoring, Source Water (GWR)
—E. COLI
July 16, 2014 – April 16, 2018
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2014 – June 30, 2017
ResolvedMonitoring, Repeat Major (TCR)
—Coliform (TCR)
July 1, 2014 – July 31, 2014
ResolvedMonitoring, Routine Minor (TCR)
—Coliform (TCR)
May 1, 2014 – May 31, 2014
ResolvedMonitoring, Repeat Minor (TCR)
—Coliform (TCR)
August 1, 2013 – August 31, 2013
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2013 – June 30, 2017
ResolvedMonitoring, Routine Minor (TCR)
—Coliform (TCR)
July 1, 2013 – July 31, 2013
ResolvedMonitoring, Source Water (GWR)
—E. COLI
June 1, 2013 – June 30, 2013
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
November 1, 2012 – November 30, 2012
ResolvedMonitoring, Source Water (GWR)
—E. COLI
October 1, 2012 – October 31, 2012
ResolvedMonitoring, Repeat Major (TCR)
—Coliform (TCR)
October 1, 2012 – October 31, 2012
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
June 1, 2012 – June 30, 2012
ResolvedMonitoring, Source Water (GWR)
—E. COLI
May 1, 2012 – May 31, 2012
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
April 1, 2012 – April 30, 2012
ResolvedMonitoring and Reporting (DBP)
—TTHM
January 1, 2012 – December 31, 2012
ResolvedMonitoring and Reporting (DBP)
—Total Haloacetic Acids (HAA5)
January 1, 2012 – December 31, 2012
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
December 1, 2011 – December 31, 2011
ResolvedMonitoring, Routine Minor (TCR)
—Coliform (TCR)
October 1, 2011 – October 31, 2011
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
May 1, 2011 – May 31, 2011
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
April 1, 2011 – April 30, 2011
ResolvedMonitoring, Source Water (GWR)
—E. COLI
January 1, 2011 – January 31, 2011
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
November 1, 2010 – November 30, 2010
ResolvedMonitoring, Repeat Major (TCR)
—Coliform (TCR)
October 1, 2010 – October 31, 2010
ResolvedMonitoring, Source Water (GWR)
—E. COLI
August 1, 2010 – August 31, 2010
ResolvedMonitoring, Repeat Minor (TCR)
—Coliform (TCR)
August 1, 2010 – August 31, 2010
ResolvedMonitoring, Repeat Major (TCR)
—Coliform (TCR)
August 1, 2010 – August 31, 2010
ResolvedMaximum Contaminant Level Violation, Monthly (TCR)
Health-basedColiform (TCR)
August 1, 2010 – August 31, 2010
ResolvedFollow-up Or Routine LCR Tap M/R
—Lead and Copper Rule
July 1, 2010 – November 18, 2010
ResolvedMonitoring, Source Water (GWR)
—E. COLI
May 1, 2010 – May 31, 2010
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
November 1, 2009 – November 30, 2009
ResolvedInitial Tap Sampling for Pb and Cu
—Lead and Copper Rule
October 1, 2009 – November 18, 2010
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
May 1, 2009 – May 31, 2009
ResolvedMonitoring, Routine Minor (TCR)
—Coliform (TCR)
October 1, 2008 – October 31, 2008
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
March 1, 2007 – March 31, 2007
ResolvedMonitoring, Routine Minor (TCR)
—Coliform (TCR)
August 1, 2006 – August 31, 2006
ResolvedMaximum Contaminant Level Violation, Monthly (TCR)
Health-basedColiform (TCR)
June 1, 2006 – June 30, 2006
ResolvedMonitoring, Routine Minor (TCR)
—Coliform (TCR)
May 1, 2006 – May 31, 2006
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
June 1, 2005 – June 30, 2005
ResolvedMonitoring, Regular
—Ethylbenzene
July 1, 2002 – September 30, 2002
ResolvedMonitoring, Regular
—1,1-Dichloroethylene
July 1, 2002 – September 30, 2002
ResolvedMonitoring, Regular
—p-Dichlorobenzene
July 1, 2002 – September 30, 2002
ResolvedMonitoring, Regular
—cis-1,2-Dichloroethylene
July 1, 2002 – September 30, 2002
ResolvedMonitoring, Regular
—1,1,1-Trichloroethane
July 1, 2001 – September 30, 2001
ResolvedMonitoring, Regular
—Xylenes, Total
July 1, 2001 – September 30, 2001
Resolved
Resolved addressed and confirmed by the stateUnaddressed no corrective action on record yetArchived closed in EPA's records (typically due to age or a data correction)
| Period | Violation | Contaminant / rule | Health-based | Status |
|---|---|---|---|---|
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | BHC-GAMMA | — | Resolved |
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | Methoxychlor | — | Resolved |
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | Endrin | — | Resolved |
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | Chlordane | — | Resolved |
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | Total Polychlorinated Biphenyls (PCB) | — | Resolved |
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | HEXACHLOROBENZENE | — | Resolved |
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | Heptachlor epoxide | — | Resolved |
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | Heptachlor | — | Resolved |
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | LASSO | — | Resolved |
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | Atrazine | — | Resolved |
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | Hexachlorocyclopentadiene | — | Resolved |
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | Simazine | — | Resolved |
| January 1, 2025 – March 31, 2025 | Monitoring, Regular | Toxaphene | — | Resolved |
| October 17, 2024 – July 15, 2025 | LSL Reporting | LEAD AND COPPER RULE REVISIONS | — | Resolved |
| October 17, 2024 – July 15, 2025 | LSL Inventory | LEAD AND COPPER RULE REVISIONS | Health-based | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | LASSO | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Chlordane | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | ETHYLENE DIBROMIDE | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | 1,2-DIBROMO-3-CHLOROPROPANE | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Total Polychlorinated Biphenyls (PCB) | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Pentachlorophenol | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Benzo(a)pyrene | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | HEXACHLOROBENZENE | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | 2,4,5-TP | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | 2,4-D | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Heptachlor epoxide | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Heptachlor | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Atrazine | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Carbofuran | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Hexachlorocyclopentadiene | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Di(2-ethylhexyl) phthalate | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Simazine | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | OXAMYL | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Di(2-ethylhexyl) adipate | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Diquat | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Dalapon | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Methoxychlor | — | Resolved |
| October 1, 2024 – December 31, 2024 | Monitoring, Regular | Endrin | — | Resolved |
| August 1, 2024 – August 31, 2024 | Monitoring, Routine (RTCR) | Revised Total Coliform Rule | — | Resolved |
| August 1, 2024 – August 31, 2024 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Benzo(a)pyrene | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | HEXACHLOROBENZENE | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | LASSO | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Atrazine | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Carbofuran | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Hexachlorocyclopentadiene | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Dinoseb | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Picloram | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Di(2-ethylhexyl) phthalate | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Simazine | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | OXAMYL | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Di(2-ethylhexyl) adipate | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Glyphosate | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Endothall | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Diquat | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Dalapon | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Toxaphene | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Methoxychlor | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | BHC-GAMMA | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Endrin | — | Resolved |
| July 1, 2024 – July 31, 2024 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| July 1, 2024 – September 30, 2024 | Monitoring, Regular | Total Polychlorinated Biphenyls (PCB) | — | Resolved |
| July 1, 2024 – July 31, 2024 | Monitoring, Routine (RTCR) | Revised Total Coliform Rule | — | Resolved |
| June 1, 2024 – June 30, 2024 | Monitoring, Routine (RTCR) | Revised Total Coliform Rule | — | Resolved |
| June 1, 2024 – June 30, 2024 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| April 1, 2024 – June 30, 2024 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| April 1, 2024 – June 30, 2024 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| January 1, 2024 – March 31, 2024 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| January 1, 2024 – March 31, 2024 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| October 2, 2023 – June 30, 2024 | Consumer Confidence Report Inadequate Reporting | Consumer Confidence Rule | — | Resolved |
| October 1, 2023 – December 31, 2023 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| July 13, 2023 | Monitoring, Source Water (GWR) | E. COLI | — | Unaddressed |
| July 1, 2023 – July 31, 2023 | Monitoring, Routine (RTCR) | Revised Total Coliform Rule | — | Resolved |
| July 1, 2023 – September 30, 2023 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| July 1, 2023 – September 30, 2023 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| July 1, 2023 – September 30, 2023 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| April 1, 2023 – June 30, 2023 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| April 1, 2023 – June 30, 2023 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| April 1, 2023 – June 30, 2023 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| January 1, 2023 – March 31, 2023 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| January 1, 2023 – March 31, 2023 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| January 1, 2023 – January 31, 2023 | Monitoring, Routine (RTCR) | Revised Total Coliform Rule | — | Resolved |
| October 2, 2022 – June 30, 2024 | Consumer Confidence Report Inadequate Reporting | Consumer Confidence Rule | — | Resolved |
| October 1, 2022 – December 31, 2022 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| July 1, 2021 – July 31, 2021 | Monitoring, Routine (RTCR) | Revised Total Coliform Rule | — | Resolved |
| July 1, 2021 – June 30, 2024 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| July 1, 2021 – September 30, 2021 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| October 2, 2020 – June 30, 2024 | Consumer Confidence Report Inadequate Reporting | Consumer Confidence Rule | — | Resolved |
| October 1, 2020 – December 31, 2020 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| January 1, 2020 – March 31, 2020 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| January 1, 2020 – January 31, 2020 | Monitoring, Routine (RTCR) | Revised Total Coliform Rule | — | Resolved |
| December 2, 2019 – June 30, 2024 | Consumer Confidence Report Inadequate Reporting | Consumer Confidence Rule | — | Resolved |
| November 1, 2016 – November 30, 2016 | Maximum Contaminant Level Violation, E. coli (RTCR) | Revised Total Coliform Rule | Health-based | Resolved |
| July 1, 2016 – June 30, 2017 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| November 1, 2015 – November 30, 2015 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| October 1, 2015 – December 31, 2015 | Monitoring and Reporting (DBP) | Chlorine | — | Archived |
| September 18, 2015 – April 16, 2018 | Monitoring, Source Water (GWR) | E. COLI | — | Resolved |
| August 1, 2015 – August 31, 2015 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| July 24, 2015 – April 16, 2018 | Monitoring, Source Water (GWR) | E. COLI | — | Resolved |
| July 1, 2015 – June 30, 2017 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| July 1, 2015 – September 30, 2015 | Monitoring and Reporting (DBP) | Chlorine | — | Archived |
| July 1, 2015 – July 31, 2015 | Monitoring, Repeat Major (TCR) | Coliform (TCR) | — | Resolved |
| November 1, 2014 – November 30, 2014 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| July 16, 2014 – April 16, 2018 | Monitoring, Source Water (GWR) | E. COLI | — | Resolved |
| July 1, 2014 – June 30, 2017 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| July 1, 2014 – July 31, 2014 | Monitoring, Repeat Major (TCR) | Coliform (TCR) | — | Resolved |
| May 1, 2014 – May 31, 2014 | Monitoring, Routine Minor (TCR) | Coliform (TCR) | — | Resolved |
| August 1, 2013 – August 31, 2013 | Monitoring, Repeat Minor (TCR) | Coliform (TCR) | — | Resolved |
| July 1, 2013 – June 30, 2017 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| July 1, 2013 – July 31, 2013 | Monitoring, Routine Minor (TCR) | Coliform (TCR) | — | Resolved |
| June 1, 2013 – June 30, 2013 | Monitoring, Source Water (GWR) | E. COLI | — | Resolved |
| November 1, 2012 – November 30, 2012 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| October 1, 2012 – October 31, 2012 | Monitoring, Source Water (GWR) | E. COLI | — | Resolved |
| October 1, 2012 – October 31, 2012 | Monitoring, Repeat Major (TCR) | Coliform (TCR) | — | Resolved |
| June 1, 2012 – June 30, 2012 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| May 1, 2012 – May 31, 2012 | Monitoring, Source Water (GWR) | E. COLI | — | Resolved |
| April 1, 2012 – April 30, 2012 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| January 1, 2012 – December 31, 2012 | Monitoring and Reporting (DBP) | TTHM | — | Resolved |
| January 1, 2012 – December 31, 2012 | Monitoring and Reporting (DBP) | Total Haloacetic Acids (HAA5) | — | Resolved |
| December 1, 2011 – December 31, 2011 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| October 1, 2011 – October 31, 2011 | Monitoring, Routine Minor (TCR) | Coliform (TCR) | — | Resolved |
| May 1, 2011 – May 31, 2011 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| April 1, 2011 – April 30, 2011 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| January 1, 2011 – January 31, 2011 | Monitoring, Source Water (GWR) | E. COLI | — | Resolved |
| November 1, 2010 – November 30, 2010 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| October 1, 2010 – October 31, 2010 | Monitoring, Repeat Major (TCR) | Coliform (TCR) | — | Resolved |
| August 1, 2010 – August 31, 2010 | Monitoring, Source Water (GWR) | E. COLI | — | Resolved |
| August 1, 2010 – August 31, 2010 | Monitoring, Repeat Minor (TCR) | Coliform (TCR) | — | Resolved |
| August 1, 2010 – August 31, 2010 | Monitoring, Repeat Major (TCR) | Coliform (TCR) | — | Resolved |
| August 1, 2010 – August 31, 2010 | Maximum Contaminant Level Violation, Monthly (TCR) | Coliform (TCR) | Health-based | Resolved |
| July 1, 2010 – November 18, 2010 | Follow-up Or Routine LCR Tap M/R | Lead and Copper Rule | — | Resolved |
| May 1, 2010 – May 31, 2010 | Monitoring, Source Water (GWR) | E. COLI | — | Resolved |
| November 1, 2009 – November 30, 2009 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| October 1, 2009 – November 18, 2010 | Initial Tap Sampling for Pb and Cu | Lead and Copper Rule | — | Resolved |
| May 1, 2009 – May 31, 2009 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| October 1, 2008 – October 31, 2008 | Monitoring, Routine Minor (TCR) | Coliform (TCR) | — | Resolved |
| March 1, 2007 – March 31, 2007 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| August 1, 2006 – August 31, 2006 | Monitoring, Routine Minor (TCR) | Coliform (TCR) | — | Resolved |
| June 1, 2006 – June 30, 2006 | Maximum Contaminant Level Violation, Monthly (TCR) | Coliform (TCR) | Health-based | Resolved |
| May 1, 2006 – May 31, 2006 | Monitoring, Routine Minor (TCR) | Coliform (TCR) | — | Resolved |
| June 1, 2005 – June 30, 2005 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| July 1, 2002 – September 30, 2002 | Monitoring, Regular | Ethylbenzene | — | Resolved |
| July 1, 2002 – September 30, 2002 | Monitoring, Regular | 1,1-Dichloroethylene | — | Resolved |
| July 1, 2002 – September 30, 2002 | Monitoring, Regular | p-Dichlorobenzene | — | Resolved |
| July 1, 2002 – September 30, 2002 | Monitoring, Regular | cis-1,2-Dichloroethylene | — | Resolved |
| July 1, 2001 – September 30, 2001 | Monitoring, Regular | 1,1,1-Trichloroethane | — | Resolved |
| July 1, 2001 – September 30, 2001 | Monitoring, Regular | Xylenes, Total | — | Resolved |
Resolved addressed and confirmed by the stateUnaddressed no corrective action on record yetArchived closed in EPA's records (typically due to age or a data correction)
Enforcement actions
- August 25, 2025State Compliance achieved8 linked violations
- August 25, 2025State Compliance achieved8 linked violations
- August 25, 2025State Compliance achieved3 linked violations
- August 25, 2025State Compliance achieved10 linked violations
- August 25, 2025State Compliance achieved2 linked violations
- June 3, 2025State Violation/Reminder Notice14 linked violations
- June 3, 2025State Public Notification requested14 linked violations
- May 19, 2025State Compliance achieved29 linked violations
- April 10, 2025State Compliance achieved30 linked violations
- October 11, 2024State Compliance achieved11 linked violations
- October 11, 2024State Compliance achieved11 linked violations
- October 11, 2024State Compliance achieved2 linked violations
- September 26, 2024State Public Notification requested4 linked violations
- July 17, 2024State Public Notification requested2 linked violations
- June 30, 2024State Public Notification received2 linked violations
- June 30, 2024State Public Notification received2 linked violations
- June 30, 2024State Public Notification received2 linked violations
- June 30, 2024State Public Notification received3 linked violations
- June 30, 2024State Public Notification received2 linked violations
- June 30, 2024State Public Notification received2 linked violations
- June 30, 2024State Public Notification received2 linked violations
- June 30, 2024State Compliance achieved1 linked violation
- June 18, 2024State Violation/Reminder Notice3 linked violations
- May 20, 2024State Compliance achieved10 linked violations
- May 15, 2024State Public Notification requested9 linked violations
- January 4, 2024State Compliance achieved10 linked violations
- December 15, 2023State Public Notification requested9 linked violations
- October 19, 2023State Public Notification requested7 linked violations
- September 22, 2023State Public Notification requested2 linked violations
- July 21, 2023State Violation/Reminder Notice1 linked violation
- April 4, 2023State Public Notification requested2 linked violations
- February 14, 2023State Compliance achieved3 linked violations
- January 6, 2023State Public Notification requested2 linked violations
- January 6, 2023State Violation/Reminder Notice2 linked violations
- July 19, 2022State Compliance achieved3 linked violations
- September 17, 2021State Public Notification requested4 linked violations
- September 17, 2021State Public Notification requested11 linked violations
- June 17, 2020State Public Notification requested11 linked violations
- November 8, 2017State Compliance achieved2 linked violations
- December 13, 2016State Boil Water Order3 linked violations
- August 4, 2016State Compliance achieved1 linked violation
- March 18, 2016State Violation/Reminder Notice2 linked violations
- March 18, 2016State Violation/Reminder Notice2 linked violations
- March 14, 2016State Violation/Reminder Notice10 linked violations
- January 6, 2016State Violation/Reminder Notice10 linked violations
- October 23, 2015State Public Notification received5 linked violations
- October 12, 2015State Public Notification requested5 linked violations
- October 7, 2015State Public Notification requested15 linked violations
- July 21, 2015State Public Notification requested2 linked violations
- June 29, 2015State Violation/Reminder Notice4 linked violations
- January 14, 2015State Violation/Reminder Notice3 linked violations
- January 9, 2015State Public Notification requested10 linked violations
- August 29, 2014State Violation/Reminder Notice17 linked violations
- July 10, 2014State Violation/Reminder Notice10 linked violations
- August 29, 2013Federal Compliance achieved1 linked violation
- November 28, 2012Federal Compliance achieved3 linked violations
- October 4, 2010Federal Compliance achieved1 linked violation
- September 10, 2010State Public Notification requested17 linked violations
- July 1, 2010Federal Compliance achieved1 linked violation
- April 8, 2010State Violation/Reminder Notice18 linked violations
- March 8, 2010State Public Notification received2 linked violations
- November 1, 2008State Compliance achieved3 linked violations
- April 18, 2007State Public Notification requested18 linked violations
- April 1, 2007State Compliance achieved18 linked violations
- August 30, 2006State Public Notification requested4 linked violations
- July 21, 2006State Violation/Reminder Notice6 linked violations
- May 25, 2006State Violation/Reminder Notice1 linked violation
- November 16, 2005State Public Notification requested8 linked violations
- November 16, 2005State Violation/Reminder Notice6 linked violations
- August 15, 2005State Public Notification requested5 linked violations
- July 22, 2005State Public Notification received5 linked violations
- February 3, 2004State Compliance achieved22 linked violations
- January 26, 2004State Public Notification received21 linked violations
- January 22, 2004State Site Visit for enforcement purposes22 linked violations
- October 22, 2003State Violation/Reminder Notice2 linked violations
- October 22, 2003State Public Notification requested2 linked violations
- December 2, 2002State Administrative/Compliance Order with penalty issued21 linked violations
Contact
SKYLINE MHP
405-323-8458
DEL CITY, OK 73115