Drinking Water Compliance OS

BINGER, OK · Caddo County

BINGER PWA Water System

Current status

No open violations on record as of July 4, 2026.

This system's next federally required Consumer Confidence Report is due July 1, 2027, under the EPA's revised reporting rule.

Data sourced from the EPA ECHO database (SDWA bulk download), last refreshed July 4, 2026. This is a record-keeping and public-information tool — it does not replace Oklahoma’s official records. Always confirm current status with Oklahoma before making decisions based on this information.

System facts

System ID (PWSID)
OK2000803
System type
Community Water System
Population served
708
Service connections
379
Ownership
local government
Water source
groundwater (wells)

Violation history

  • LSL Reporting

    LEAD AND COPPER RULE REVISIONS

    October 17, 2024 – July 15, 2025

    Resolved
  • LSL Inventory

    Health-based

    LEAD AND COPPER RULE REVISIONS

    October 17, 2024 – July 15, 2025

    Resolved
  • Monitoring, Routine (RTCR)

    Revised Total Coliform Rule

    November 1, 2023 – November 30, 2023

    Resolved
  • Monitoring, Routine (RTCR)

    Revised Total Coliform Rule

    June 1, 2021 – June 30, 2021

    Resolved
  • Monitoring and Reporting (DBP)

    Chlorine

    April 1, 2021 – June 30, 2021

    Resolved
  • Monitoring, Regular

    1,2-Dichloroethane

    January 1, 2015 – December 31, 2015

    Resolved
  • Monitoring, Regular

    1,1,1-Trichloroethane

    January 1, 2015 – December 31, 2015

    Resolved
  • Monitoring, Regular

    CHLOROBENZENE

    January 1, 2015 – December 31, 2015

    Resolved
  • Monitoring, Regular

    Ethylbenzene

    January 1, 2015 – December 31, 2015

    Resolved
  • Monitoring, Regular

    1,2,4-Trichlorobenzene

    January 1, 2015 – December 31, 2015

    Resolved
  • Monitoring, Regular

    Xylenes, Total

    January 1, 2015 – December 31, 2015

    Resolved
  • Monitoring, Regular

    DICHLOROMETHANE

    January 1, 2015 – December 31, 2015

    Resolved
  • Monitoring, Regular

    p-Dichlorobenzene

    January 1, 2015 – December 31, 2015

    Resolved
  • Monitoring, Regular

    o-Dichlorobenzene

    January 1, 2015 – December 31, 2015

    Resolved
  • Monitoring, Regular

    1,1-Dichloroethylene

    January 1, 2015 – December 31, 2015

    Resolved
  • Monitoring, Regular

    trans-1,2-Dichloroethylene

    January 1, 2015 – December 31, 2015

    Resolved
  • Monitoring, Regular

    1,2,4-Trichlorobenzene

    October 1, 2010 – December 31, 2010

    Resolved
  • Monitoring, Regular

    Xylenes, Total

    October 1, 2010 – December 31, 2010

    Resolved
  • Monitoring, Regular

    DICHLOROMETHANE

    October 1, 2010 – December 31, 2010

    Resolved
  • Monitoring, Regular

    1,2-Dichloroethane

    October 1, 2010 – December 31, 2010

    Resolved
  • Monitoring, Regular

    Carbon tetrachloride

    October 1, 2010 – December 31, 2010

    Resolved
  • Monitoring, Regular

    CHLOROBENZENE

    October 1, 2010 – December 31, 2010

    Resolved
  • Monitoring, Regular

    Benzene

    October 1, 2010 – December 31, 2010

    Resolved
  • Monitoring, Regular

    Toluene

    October 1, 2010 – December 31, 2010

    Resolved
  • Monitoring, Regular

    Ethylbenzene

    October 1, 2010 – December 31, 2010

    Resolved
  • Monitoring, Regular

    Styrene

    October 1, 2010 – December 31, 2010

    Resolved
  • Monitoring, Regular

    Atrazine

    January 1, 2005 – December 31, 2007

    Resolved
  • Initial Tap Sampling for Pb and Cu

    Lead and Copper Rule

    January 1, 1994 – October 26, 1998

    Resolved
  • Monitoring, Routine Major (TCR)

    Coliform (TCR)

    July 1, 1992 – July 31, 1992

    Resolved

Resolved addressed and confirmed by the state

Enforcement actions

Contact

BINGER PWA

405-656-2426

BINGER, OK 73009