SANDY HOOK, CT · Fairfield County
55 SUGAR STREET Water System
Current status
No open violations on record as of July 4, 2026.
This system's next federally required Consumer Confidence Report is due July 1, 2027, under the EPA's revised reporting rule.
Data sourced from the EPA ECHO database (SDWA bulk download), last refreshed July 4, 2026. This is a record-keeping and public-information tool — it does not replace Connecticut’s official records. Always confirm current status with Connecticut before making decisions based on this information.
System facts
- System ID (PWSID)
- CT0970071
- System type
- Community Water System
- Population served
- 158
- Service connections
- 62
- Ownership
- privately owned
- Water source
- groundwater (wells)
Violation history
Failure to Conduct Assessment Monitoring
—E. COLI
November 1, 2025 – November 30, 2025
ArchivedFailure to Conduct Assessment Monitoring
—E. COLI
November 1, 2025 – November 30, 2025
ArchivedLead Consumer Notice
—Lead and Copper Rule
March 31, 2024 – May 13, 2024
ResolvedConsumer Confidence Report Inadequate Reporting
—Consumer Confidence Rule
August 10, 2023 – October 19, 2023
ResolvedFailure to Conduct Assessment Monitoring
—E. COLI
August 1, 2023 – August 31, 2023
ResolvedMonitoring, Regular
—Gross Alpha, Excl. Radon and U
January 1, 2023 – March 31, 2023
ResolvedPublic Notification Violation for NPDWR Violation
—Public Notice
November 13, 2022 – November 25, 2022
ResolvedMonitoring, Routine (RTCR)
—Revised Total Coliform Rule
November 1, 2022 – November 30, 2022
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2022 – November 29, 2022
ResolvedMonitoring, Regular
—Combined Radium (-226 and -228)
July 1, 2022 – September 30, 2022
ResolvedMonitoring, Routine (RTCR)
—Revised Total Coliform Rule
July 1, 2022 – July 31, 2022
ResolvedMonitoring and Reporting (DBP)
—Chlorine
June 1, 2022 – June 30, 2022
ResolvedMonitoring, Regular
—Gross Alpha, Excl. Radon and U
April 1, 2022 – June 30, 2022
ResolvedMonitoring, Routine (RTCR)
—Revised Total Coliform Rule
March 1, 2022 – March 31, 2022
ResolvedMonitoring and Reporting (DBP)
—Chlorine
January 1, 2022 – March 31, 2022
ResolvedFollow-up Or Routine LCR Tap M/R
—Lead and Copper Rule
October 1, 2021 – December 31, 2022
ResolvedMonitoring and Reporting (DBP)
—Total Haloacetic Acids (HAA5)
September 1, 2021 – August 31, 2022
ResolvedConsumer Confidence Report Inadequate Reporting
—Consumer Confidence Rule
August 10, 2021 – November 25, 2022
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2021 – November 25, 2022
ResolvedMonitoring and Reporting (DBP)
—Chlorine
March 1, 2021 – March 31, 2021
ResolvedConsumer Confidence Report Inadequate Reporting
—Consumer Confidence Rule
August 10, 2020 – November 25, 2022
ResolvedPublic Notification Violation for NPDWR Violation
—Public Notice
December 30, 2018 – February 27, 2019
ResolvedConsumer Confidence Report Inadequate Reporting
—Consumer Confidence Rule
August 10, 2017 – April 19, 2018
ResolvedPublic Notification Violation for NPDWR Violation
—Public Notice
July 1, 2017 – April 15, 2018
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
July 1, 2017 – July 31, 2017
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2017 – April 19, 2018
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
June 1, 2017 – June 30, 2017
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
May 1, 2017 – May 31, 2017
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
April 1, 2017 – April 30, 2017
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
March 1, 2017 – March 31, 2017
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
January 1, 2017 – January 31, 2017
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
December 1, 2016 – December 31, 2016
ResolvedMonitoring and Reporting (DBP)
—TTHM
October 1, 2016 – September 30, 2017
ResolvedMonitoring and Reporting (DBP)
—Total Haloacetic Acids (HAA5)
October 1, 2016 – September 30, 2017
ResolvedPublic Notification Violation for NPDWR Violation
—Public Notice
August 14, 2016 – April 15, 2018
ResolvedConsumer Confidence Report Inadequate Reporting
—Consumer Confidence Rule
August 10, 2016 – June 24, 2016
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2016 – June 14, 2016
ResolvedMaximum Contaminant Level Violation, Average
Health-basedCombined Radium (-226 and -228)
April 1, 2016 – June 30, 2016
ResolvedMaximum Contaminant Level Violation, Average
Health-basedCombined Radium (-226 and -228)
January 1, 2016 – March 31, 2016
ResolvedFollow-up Or Routine LCR Tap M/R
—Lead and Copper Rule
October 1, 2015 – December 31, 2018
ResolvedConsumer Confidence Report Inadequate Reporting
—Consumer Confidence Rule
August 10, 2014 – August 24, 2014
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2014 – August 24, 2014
ResolvedConsumer Confidence Report Inadequate Reporting
—Consumer Confidence Rule
August 10, 2013 – November 13, 2013
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2013 – November 13, 2013
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
June 1, 2013 – June 30, 2013
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
November 1, 2012 – November 30, 2012
ResolvedTreatment Technique (SWTR and GWR)
Health-basedGroundwater Rule
October 1, 2012 – October 31, 2012
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
October 1, 2012 – October 31, 2012
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
September 1, 2012 – September 30, 2012
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
May 1, 2012 – May 31, 2012
ResolvedTreatment Technique (SWTR and GWR)
Health-basedGroundwater Rule
May 1, 2012 – May 31, 2012
ResolvedMonitoring, Regular
—Combined Uranium
April 1, 2012 – June 30, 2012
ResolvedMonitoring, Regular
—Gross Alpha, Excl. Radon and U
April 1, 2012 – June 30, 2012
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
April 1, 2012 – April 30, 2012
ResolvedMonitoring, Regular
—Combined Radium (-226 and -228)
April 1, 2012 – June 30, 2012
ResolvedMonitoring, Routine Major (TCR)
—Coliform (TCR)
March 1, 2012 – March 31, 2012
ResolvedMonitoring and Reporting (DBP)
—Chlorine
January 1, 2012 – March 31, 2012
ResolvedTreatment Technique (SWTR and GWR)
Health-basedGroundwater Rule
September 1, 2011 – September 30, 2011
ResolvedConsumer Confidence Report Inadequate Reporting
—Consumer Confidence Rule
August 10, 2011 – September 6, 2016
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2011 – June 22, 2012
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
June 1, 2011 – June 30, 2011
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
December 1, 2010 – December 31, 2010
ResolvedMonitoring of Treatment (SWTR-Unfilt/GWR)
—Groundwater Rule
September 1, 2010 – September 30, 2010
ResolvedPublic Notification Violation for NPDWR Violation
—Public Notice
July 1, 2009 – June 14, 2011
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2009 – August 10, 2009
ResolvedMaximum Contaminant Level Violation, Monthly (TCR)
Health-basedColiform (TCR)
July 1, 2009 – July 31, 2009
ResolvedMaximum Contaminant Level Violation, Average
Health-basedCombined Radium (-226 and -228)
July 1, 2008 – September 30, 2008
ResolvedMaximum Contaminant Level Violation, Average
Health-basedCombined Uranium
April 1, 2008 – June 30, 2008
ResolvedMaximum Contaminant Level Violation, Average
Health-basedCombined Radium (-226 and -228)
January 1, 2008 – March 31, 2008
ResolvedMaximum Contaminant Level Violation, Average
Health-basedCombined Radium (-226 and -228)
October 1, 2007 – December 31, 2007
ResolvedPublic Notification Violation for NPDWR Violation
—Public Notice
August 12, 2007 – June 14, 2011
ResolvedConsumer Confidence Report Complete Failure to Report
—Consumer Confidence Rule
July 1, 2006 – August 14, 2006
ResolvedMonitoring, Regular
—Combined Uranium
July 1, 2006 – September 30, 2006
ResolvedMaximum Contaminant Level Violation, Average
Health-basedCombined Radium (-226 and -228)
July 1, 2006 – September 30, 2006
ResolvedMonitoring, Regular
—Combined Radium (-226 and -228)
April 1, 2006 – June 30, 2006
Resolved
Archived closed in EPA's records (typically due to age or a data correction)Resolved addressed and confirmed by the state
| Period | Violation | Contaminant / rule | Health-based | Status |
|---|---|---|---|---|
| November 1, 2025 – November 30, 2025 | Failure to Conduct Assessment Monitoring | E. COLI | — | Archived |
| November 1, 2025 – November 30, 2025 | Failure to Conduct Assessment Monitoring | E. COLI | — | Archived |
| March 31, 2024 – May 13, 2024 | Lead Consumer Notice | Lead and Copper Rule | — | Resolved |
| August 10, 2023 – October 19, 2023 | Consumer Confidence Report Inadequate Reporting | Consumer Confidence Rule | — | Resolved |
| August 1, 2023 – August 31, 2023 | Failure to Conduct Assessment Monitoring | E. COLI | — | Resolved |
| January 1, 2023 – March 31, 2023 | Monitoring, Regular | Gross Alpha, Excl. Radon and U | — | Resolved |
| November 13, 2022 – November 25, 2022 | Public Notification Violation for NPDWR Violation | Public Notice | — | Resolved |
| November 1, 2022 – November 30, 2022 | Monitoring, Routine (RTCR) | Revised Total Coliform Rule | — | Resolved |
| July 1, 2022 – November 29, 2022 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| July 1, 2022 – September 30, 2022 | Monitoring, Regular | Combined Radium (-226 and -228) | — | Resolved |
| July 1, 2022 – July 31, 2022 | Monitoring, Routine (RTCR) | Revised Total Coliform Rule | — | Resolved |
| June 1, 2022 – June 30, 2022 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| April 1, 2022 – June 30, 2022 | Monitoring, Regular | Gross Alpha, Excl. Radon and U | — | Resolved |
| March 1, 2022 – March 31, 2022 | Monitoring, Routine (RTCR) | Revised Total Coliform Rule | — | Resolved |
| January 1, 2022 – March 31, 2022 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| October 1, 2021 – December 31, 2022 | Follow-up Or Routine LCR Tap M/R | Lead and Copper Rule | — | Resolved |
| September 1, 2021 – August 31, 2022 | Monitoring and Reporting (DBP) | Total Haloacetic Acids (HAA5) | — | Resolved |
| August 10, 2021 – November 25, 2022 | Consumer Confidence Report Inadequate Reporting | Consumer Confidence Rule | — | Resolved |
| July 1, 2021 – November 25, 2022 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| March 1, 2021 – March 31, 2021 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| August 10, 2020 – November 25, 2022 | Consumer Confidence Report Inadequate Reporting | Consumer Confidence Rule | — | Resolved |
| December 30, 2018 – February 27, 2019 | Public Notification Violation for NPDWR Violation | Public Notice | — | Resolved |
| August 10, 2017 – April 19, 2018 | Consumer Confidence Report Inadequate Reporting | Consumer Confidence Rule | — | Resolved |
| July 1, 2017 – April 15, 2018 | Public Notification Violation for NPDWR Violation | Public Notice | — | Resolved |
| July 1, 2017 – July 31, 2017 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| July 1, 2017 – April 19, 2018 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| June 1, 2017 – June 30, 2017 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| May 1, 2017 – May 31, 2017 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| April 1, 2017 – April 30, 2017 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| March 1, 2017 – March 31, 2017 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| January 1, 2017 – January 31, 2017 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| December 1, 2016 – December 31, 2016 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| October 1, 2016 – September 30, 2017 | Monitoring and Reporting (DBP) | TTHM | — | Resolved |
| October 1, 2016 – September 30, 2017 | Monitoring and Reporting (DBP) | Total Haloacetic Acids (HAA5) | — | Resolved |
| August 14, 2016 – April 15, 2018 | Public Notification Violation for NPDWR Violation | Public Notice | — | Resolved |
| August 10, 2016 – June 24, 2016 | Consumer Confidence Report Inadequate Reporting | Consumer Confidence Rule | — | Resolved |
| July 1, 2016 – June 14, 2016 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| April 1, 2016 – June 30, 2016 | Maximum Contaminant Level Violation, Average | Combined Radium (-226 and -228) | Health-based | Resolved |
| January 1, 2016 – March 31, 2016 | Maximum Contaminant Level Violation, Average | Combined Radium (-226 and -228) | Health-based | Resolved |
| October 1, 2015 – December 31, 2018 | Follow-up Or Routine LCR Tap M/R | Lead and Copper Rule | — | Resolved |
| August 10, 2014 – August 24, 2014 | Consumer Confidence Report Inadequate Reporting | Consumer Confidence Rule | — | Resolved |
| July 1, 2014 – August 24, 2014 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| August 10, 2013 – November 13, 2013 | Consumer Confidence Report Inadequate Reporting | Consumer Confidence Rule | — | Resolved |
| July 1, 2013 – November 13, 2013 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| June 1, 2013 – June 30, 2013 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| November 1, 2012 – November 30, 2012 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| October 1, 2012 – October 31, 2012 | Treatment Technique (SWTR and GWR) | Groundwater Rule | Health-based | Resolved |
| October 1, 2012 – October 31, 2012 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| September 1, 2012 – September 30, 2012 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| May 1, 2012 – May 31, 2012 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| May 1, 2012 – May 31, 2012 | Treatment Technique (SWTR and GWR) | Groundwater Rule | Health-based | Resolved |
| April 1, 2012 – June 30, 2012 | Monitoring, Regular | Combined Uranium | — | Resolved |
| April 1, 2012 – June 30, 2012 | Monitoring, Regular | Gross Alpha, Excl. Radon and U | — | Resolved |
| April 1, 2012 – April 30, 2012 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| April 1, 2012 – June 30, 2012 | Monitoring, Regular | Combined Radium (-226 and -228) | — | Resolved |
| March 1, 2012 – March 31, 2012 | Monitoring, Routine Major (TCR) | Coliform (TCR) | — | Resolved |
| January 1, 2012 – March 31, 2012 | Monitoring and Reporting (DBP) | Chlorine | — | Resolved |
| September 1, 2011 – September 30, 2011 | Treatment Technique (SWTR and GWR) | Groundwater Rule | Health-based | Resolved |
| August 10, 2011 – September 6, 2016 | Consumer Confidence Report Inadequate Reporting | Consumer Confidence Rule | — | Resolved |
| July 1, 2011 – June 22, 2012 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| June 1, 2011 – June 30, 2011 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| December 1, 2010 – December 31, 2010 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| September 1, 2010 – September 30, 2010 | Monitoring of Treatment (SWTR-Unfilt/GWR) | Groundwater Rule | — | Resolved |
| July 1, 2009 – June 14, 2011 | Public Notification Violation for NPDWR Violation | Public Notice | — | Resolved |
| July 1, 2009 – August 10, 2009 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| July 1, 2009 – July 31, 2009 | Maximum Contaminant Level Violation, Monthly (TCR) | Coliform (TCR) | Health-based | Resolved |
| July 1, 2008 – September 30, 2008 | Maximum Contaminant Level Violation, Average | Combined Radium (-226 and -228) | Health-based | Resolved |
| April 1, 2008 – June 30, 2008 | Maximum Contaminant Level Violation, Average | Combined Uranium | Health-based | Resolved |
| January 1, 2008 – March 31, 2008 | Maximum Contaminant Level Violation, Average | Combined Radium (-226 and -228) | Health-based | Resolved |
| October 1, 2007 – December 31, 2007 | Maximum Contaminant Level Violation, Average | Combined Radium (-226 and -228) | Health-based | Resolved |
| August 12, 2007 – June 14, 2011 | Public Notification Violation for NPDWR Violation | Public Notice | — | Resolved |
| July 1, 2006 – August 14, 2006 | Consumer Confidence Report Complete Failure to Report | Consumer Confidence Rule | — | Resolved |
| July 1, 2006 – September 30, 2006 | Monitoring, Regular | Combined Uranium | — | Resolved |
| July 1, 2006 – September 30, 2006 | Maximum Contaminant Level Violation, Average | Combined Radium (-226 and -228) | Health-based | Resolved |
| April 1, 2006 – June 30, 2006 | Monitoring, Regular | Combined Radium (-226 and -228) | — | Resolved |
Archived closed in EPA's records (typically due to age or a data correction)Resolved addressed and confirmed by the state
Enforcement actions
- December 31, 2024State Compliance achieved2 linked violations
- December 31, 2024State Compliance achieved2 linked violations
- May 13, 2024State Compliance achieved2 linked violations
- April 29, 2024State Public Notification received2 linked violations
- April 26, 2024State Public Notification requested2 linked violations
- April 26, 2024State Public Notification requested2 linked violations
- January 23, 2024State Public Notification requested4 linked violations
- January 23, 2024State Violation/Reminder Notice4 linked violations
- December 31, 2023State Compliance achieved2 linked violations
- October 19, 2023State Compliance achieved4 linked violations
- September 30, 2023State Compliance achieved2 linked violations
- September 7, 2023State Violation/Reminder Notice2 linked violations
- March 24, 2023State Public Notification received2 linked violations
- March 24, 2023State Public Notification received2 linked violations
- March 24, 2023State Public Notification received27 linked violations
- March 24, 2023State Public Notification received2 linked violations
- March 2, 2023State Violation/Reminder Notice2 linked violations
- March 2, 2023State Violation/Reminder Notice2 linked violations
- March 2, 2023State Violation/Reminder Notice2 linked violations
- March 2, 2023State Public Notification requested2 linked violations
- March 2, 2023State Violation/Reminder Notice2 linked violations
- March 2, 2023State Public Notification requested2 linked violations
- March 2, 2023State Public Notification requested2 linked violations
- March 2, 2023State Public Notification requested2 linked violations
- March 2, 2023State Public Notification requested2 linked violations
- March 2, 2023State Violation/Reminder Notice2 linked violations
- March 2, 2023State Public Notification requested2 linked violations
- March 2, 2023State Public Notification requested2 linked violations
- March 2, 2023State Public Notification requested3 linked violations
- December 31, 2022State Compliance achieved2 linked violations
- December 31, 2022State Compliance achieved5 linked violations
- December 31, 2022State Compliance achieved2 linked violations
- December 31, 2022State Compliance achieved2 linked violations
- December 31, 2022State Compliance achieved4 linked violations
- December 31, 2022State Compliance achieved4 linked violations
- December 31, 2022State Compliance achieved4 linked violations
- November 25, 2022State Compliance achieved2 linked violations
- November 25, 2022State Compliance achieved2 linked violations
- November 10, 2022State Compliance achieved2 linked violations
- October 24, 2022State Violation/Reminder Notice2 linked violations
- October 13, 2022State Public Notification requested2 linked violations
- October 13, 2022State Public Notification requested2 linked violations
- October 13, 2022State Public Notification requested2 linked violations
- October 13, 2022State Public Notification requested2 linked violations
- October 13, 2022State Public Notification requested2 linked violations
- July 6, 2022State Public Notification requested8 linked violations
- July 6, 2022State Violation/Reminder Notice8 linked violations
- March 31, 2022State Compliance achieved2 linked violations
- January 19, 2022State Public Notification requested2 linked violations
- December 31, 2021State Compliance achieved2 linked violations
- December 31, 2021State Compliance achieved2 linked violations
- February 1, 2021State Violation/Reminder Notice3 linked violations
- January 15, 2021State Public Notification received3 linked violations
- January 15, 2021State Public Notification received3 linked violations
- January 14, 2021State Public Notification requested6 linked violations
- January 14, 2021State Public Notification requested3 linked violations
- January 14, 2021State Public Notification requested3 linked violations
- January 14, 2021State Violation/Reminder Notice3 linked violations
- January 14, 2020State Violation/Reminder Notice3 linked violations
- December 11, 2019State Public Notification requested3 linked violations
- July 1, 2019State Public Notification received25 linked violations
- May 6, 2019State Violation/Reminder Notice3 linked violations
- March 18, 2019State Public Notification requested25 linked violations
- February 27, 2019State Compliance achieved6 linked violations
- February 27, 2019State Compliance achieved7 linked violations
- December 31, 2018State Compliance achieved3 linked violations
- December 29, 2017State Violation/Reminder Notice2 linked violations
- December 29, 2017State Violation/Reminder Notice2 linked violations
- October 30, 2017State Violation/Reminder Notice2 linked violations
- September 30, 2016State Compliance achieved4 linked violations
- July 14, 2016State Violation/Reminder Notice3 linked violations
- June 30, 2016State Violation/Reminder Notice3 linked violations
- June 24, 2016State Compliance achieved2 linked violations
- June 14, 2016State Compliance achieved2 linked violations
- April 6, 2016State Public Notification requested3 linked violations
- November 13, 2013State Violation/Reminder Notice5 linked violations
- July 17, 2013State Violation/Reminder Notice3 linked violations
- March 21, 2013State Public Notification received3 linked violations
- February 5, 2013State Public Notification requested2 linked violations
- February 5, 2013State Violation/Reminder Notice3 linked violations
- February 5, 2013State Violation/Reminder Notice4 linked violations
- August 6, 2012State Compliance achieved6 linked violations
- June 20, 2012State Formal Notice of Violation issued3 linked violations
- September 19, 2011State Violation/Reminder Notice3 linked violations
- June 14, 2011State Public Notification received2 linked violations
- August 20, 2010State Violation/Reminder Notice3 linked violations
- August 10, 2010State Violation/Reminder Notice22 linked violations
- August 10, 2009State Violation/Reminder Notice3 linked violations
- August 10, 2009State Compliance achieved3 linked violations
- August 10, 2009State Public Notification requested3 linked violations
- May 11, 2009State Violation/Reminder Notice3 linked violations
- December 31, 2008State Compliance achieved4 linked violations
- December 31, 2008State Compliance achieved5 linked violations
- December 15, 2008State Public Notification requested3 linked violations
- December 15, 2008State Violation/Reminder Notice3 linked violations
- December 12, 2008State Administrative/Compliance Order without penalty issued22 linked violations
- June 5, 2008State Violation/Reminder Notice4 linked violations
- December 11, 2007State Violation/Reminder Notice3 linked violations
- March 28, 2007State Public Notification requested9 linked violations
- February 6, 2007State Violation/Reminder Notice4 linked violations
- February 14, 2003State Public Notification received36 linked violations
- November 14, 1995State Civil Case concluded16 linked violations
- November 14, 1995State Public Notification received10 linked violations
- November 3, 1995State Civil Case filed in State court18 linked violations
- May 4, 1995State Administrative/Compliance Order with penalty issued17 linked violations
Contact
FIORELLA, JOSEPH
203-572-6849